| Hudson's Detroit | |
|---|---|
Hudson's Detroit in January 2026 | |
![]() Interactive map of the Hudson's Detroit area | |
General information | |
| Status | Completed |
| Location | 1208 Woodward Avenue, Detroit, MI 48226 |
| Coordinates | 42°20′02″N 83°02′53″W / 42.33389°N 83.04809°W / 42.33389; -83.04809 |
Construction started | December 14, 2017 |
| Topped-out | April 10, 2024 |
| Completed | August 22, 2025 |
| Cost | $1.4 billion |
| Owner | Bedrock Detroit |
| Height | |
| Height | 208.9 meters (685.4 ft) (Tower)[1][2] |
| Technical details | |
| Floor count | 49 (Tower) 12 (Block Building) |
| Floor area | 130,064 m2 (1,400,000 sq ft) |
| Design and construction | |
| Architects | SHoP Architects Hamilton Anderson Associates |
| Developer | Bedrock Detroit |
| Main contractor | Barton Malow |
| Other information | |
Public transit | DDOT 4 |
| Website | |
| https://www.hudsons-detroit.com/ | |
Hudson's Detroit is a landmark mixed-use building complex in downtown Detroit, Michigan, United States. It includes a 49-story, 681-foot (208 m) skyscraper, with a hotel and condominiums,[3] and a 12-story,[4] 232-foot (71 m) mid-rise building,[5][6] containing commercial offices, retail space, and a conference center. The taller tower is the second-tallest building in Detroit as well as in Michigan,[1][7] and is the first skyscraper taller than 500 feet (150 m) to be built in Detroit in the 21st century. The shorter building was completed in 2025.[8]
History

Site
Hudson's Detroit is located at 1208 Woodward Avenue in Downtown Detroit, on the block bounded by Grand River Avenue to the north, Farmer Street to the east, and Gratiot Avenue to the south. The block was previously the site of the flagship store of The J. L. Hudson Company, a local chain of department stores, for which Hudson's Detroit is named.
Built in phases between 1911 and 1946, the Hudson's flagship store was the tallest department store in the world, at 440 ft (134 m), and the second largest department store in the world by area, behind Macy's Herald Square in New York City.[9] The store closed in 1983, and was imploded in 1998, making it the tallest building to ever be demolished by controlled implosion.[10][11]
In 2001, an underground parking garage was constructed at the site, designed to support a structure of up to 18 floors on top.[12][13]
Redevelopment planning

Rock Ventures gained the rights to develop the site in 2007, initially considering it as a site for the headquarters of Quicken Loans.[11] In March 2013, after over a decade of little activity at the site, Quicken Loans founder Dan Gilbert announced a competition seeking ideas for development of the site.[14][15] The contest received 200 submissions, and was won by two architects from Italy.[16] That November, Rock Ventures hired SHoP Architects to lead the design of the development, with Detroit-based Hamilton Anderson Associates serving as a local partner.[17]
An initial design of the planned building was leaked in March 2015.[18] Rock's real estate division, by then known as Bedrock Detroit, purchased the city-owned parking garage in April 2016.[11]
When plans for the development were first revealed in February 2017, the taller tower was planned to rise 734 feet (224 m), narrowly surpassing the Renaissance Center as the tallest building in Detroit and in Michigan.[18] Its proposed height was expanded to 800 feet (240 m) in September 2017, and by 2018, Bedrock was publicly considering heightening the tower to 912 feet (278 m).[18] By 2019, plans were scaled back, shortening the tower and removing a proposed observation deck.[18][19] Its final height of roughly 680 feet (210 m) was announced in March 2020.[6][20]
Construction
Ground was broken on December 14, 2017.[21] Construction began with the removal of the underground parking garage that had been built in 2001. In March 2020, construction progress was halted due to the COVID-19 pandemic, but resumed after 45 days. In December of the same year, construction reached above the ground for the first time.[22]
Completion

The high-rise tower was topped out on April 10, 2024; two days later on April 12, the development's final name, Hudson's Detroit, was announced.[23] On April 15, General Motors announced that it would relocate its global headquarters from the Renaissance Center to the top two floors of the Block Building;[24] in November, GM expanded its planned lease to four floors.[25]
The pedestrian plaza between the buildings was dedicated Nick Gilbert Way on November 6, 2025, in honor of Dan Gilbert's late son.[26] General Motors's headquarters and showroom formally opened in the building on January 12, 2026.[27]
Description
The complex consists of two buildings: the 49-story, 681-foot (208 m) Hudson's Tower, which will contain an EDITION hotel and condominiums; and the 12-story,[4] 232-foot (71 m)[5][6] Hudson's Block Building,[28] which contains commercial offices and a conference center.[4] Between the two buildings is Nick Gilbert Way, a pedestrian plaza.[26] A 700-space underground parking garage links the two buildings.[29]
Architecture
The complex was designed by SHoP Architects in a contemporary style.
Block Building tenants
General Motors is the largest office tenant in the Block Building, with its global headquarters occupying floors 8 through 11 since January 2026.[25][27] The building includes a vehicle showroom on the ground floor,[30] and features 20-foot-tall signs with the company's logo on all four sides.[24][31][32]
Other office tenants include the headquarters of Rock Holdings, the Gilbert Family Foundation,[33] and the Ven Johnson Law Firm, and offices of Rocket Companies, JPMorgan Chase, and Accenture.[34] As of June 2026, all announced office tenants at Hudson's Detroit were previously tenants of other Downtown Detroit office buildings.[33]
Hotel
On April 17, 2024, Bedrock announced that the taller tower would consist of a five-star EDITION hotel and 97 luxury condominiums, to be completed by 2027.[35]
Gallery
References
- "Hudson's Site". Hudson's Site. Bedrock Management Services LLC. Retrieved May 22, 2022.
- Williams, Candice (April 11, 2024). "Hudson's site tower reaches final height in downtown Detroit". The Detroit News. Retrieved February 3, 2025.
- Reindl, J. C. (April 11, 2024). "Hudson's site skyscraper reaches full height, is Detroit's 2nd tallest building". Detroit Free Press. Retrieved December 4, 2025.
- Williams, Candice (October 9, 2025). "Hudson's Detroit opens office building with a 7-story atrium, lots of amenities". The Detroit News. Retrieved December 4, 2025.
- "Minutes of the Board of Zoning Appeals" (PDF). Detroit Board of Zoning Appeals. April 28, 2020.
- Mondry, Aaron (March 20, 2020). "Development news roundup: impact of coronavirus, Hudson's tower height revealed". Curbed Detroit. Archived from the original on March 23, 2020. Retrieved June 15, 2021.
- "Hudson's site tower will not be tallest in Michigan after all, CEO for Gilbert's Bedrock says". January 29, 2020.
- "Detroit Hudson's Site expected to be complete in 2024 despite challenges, changes". WXYZ. January 12, 2022. Retrieved April 18, 2022.
- "Greater Hudson Store, Detroit - SkyscraperPage.com". skyscraperpage.com. Retrieved March 12, 2021.
- "Homrich Hudson's" (PDF). Homrich. Archived from the original (PDF) on March 24, 2014. Retrieved March 24, 2014.
- Reindl, J. C.; Gallagher, John (April 27, 2016). "$15M deal OK'd for Gilbert to build on Hudson's site". Detroit Free Press. Archived from the original on April 30, 2016. Retrieved December 6, 2025.
- Abbey-Lambertz, Kate (June 12, 2013). "LOOK: These Are The Winning Hudson's Site Designs". HuffPost. Retrieved March 12, 2021.
- Sewick, Paul (November 21, 2017). "The past, present, and future of the Hudson's site". Curbed Detroit. Archived from the original on February 10, 2018. Retrieved December 6, 2025.
- "Gilbert seeks ideas for developing Hudson's site in Detroit". Detroit Free Press. February 28, 2013. Archived from the original on March 3, 2013. Retrieved December 6, 2025.
- Beshouri, Paul (February 28, 2013). "Competition to Design Future Hudson's Development is Real". Curbed Detroit. Archived from the original on May 1, 2016. Retrieved December 6, 2025.
- Bentley, Chris (July 25, 2013). "Design Competition Reimagines Detroit's Hudson's Department Store Site". The Architect’s Newspaper. Retrieved December 6, 2025.
- "New York-based SHoP Architects selected to design development at former Hudson's site in downtown Detroit". mlive. November 25, 2013. Retrieved March 12, 2021.
- Pinho, Kirk (August 7, 2019). "Bedrock: Hudson's site tower may end up not being tallest building, skydeck dropped". Crain's Detroit Business. Retrieved December 6, 2025.
- Williams, Candice (August 7, 2019). "Hudson's site tower might not be tallest in state, sky deck is out". The Detroit News. Retrieved December 6, 2025.
- Pinho, Kirk (August 7, 2019). "Bedrock: Hudson's site tower may end up not being tallest building, skydeck dropped". Crain's Detroit Business. Retrieved December 6, 2025.
- "J.L. Hudson site development starting". The Detroit News. December 14, 2017. Retrieved December 6, 2025.
- Grzelewski, Jordyn (December 10, 2020). "Construction on Bedrock's Hudson's site now above ground". The Detroit News. Retrieved March 12, 2021.
- Pinho, Kirk (April 12, 2024). "Hudson's site project gets its official name".
- "GM to move headquarters from RenCen to Hudson's site". The Detroit News. April 15, 2024. Retrieved April 15, 2024.
- "GM doubles leased space in Detroit Hudson's building to 4 floors". Detroit Free Press. November 26, 2024. Retrieved December 6, 2024.
- Williams, Candice (November 6, 2025). "Downtown Detroit Gilbert plaza's name honors late son's 'vision'". The Detroit News. Retrieved January 3, 2026.
- Ballentine, Summer; Williams, Candice (January 11, 2026). "GM nods to its heritage as it begins future at new Hudson's Detroit HQ". The Detroit News. Retrieved February 18, 2026.
- Allen, Jeremy (November 12, 2025). "Bedrock Brings Back 'Hudson's for the Holidays' in Downtown Detroit". The Michigan Chronicle. Retrieved December 27, 2025.
- "Bedrock - Hudson's Site". www.bedrockdetroit.com. Retrieved March 12, 2021.
- Charniga, Jackie (January 18, 2026). "What to know about General Motors' new Detroit headquarters". USA TODAY. Retrieved February 18, 2026.
- Reindl, J. C. (October 10, 2025). "General Motors logo affixed to top of new Hudson's office building". Detroit Free Press. Retrieved December 4, 2025.
- Heyman, Arianna (October 10, 2025). "Take a look: General Motors sign installed on Hudson's Detroit". WDIV. Retrieved December 27, 2025.
- Pinho, Kirk (October 9, 2025). "Bedrock finishes its work on Hudson's Detroit office building". Crain's Detroit Business. Retrieved December 4, 2025.
- Reindl, J. C. (November 5, 2025). "JPMorgan Chase to move into new Hudson's office building". Detroit Free Press. Retrieved December 4, 2025.
- "Luxury hotel and condos will occupy Hudson's Detroit tower". The Detroit News. April 17, 2024. Retrieved April 19, 2024.