| TMSR-LF1 | |||||
|---|---|---|---|---|---|
| Generation | IV | ||||
| Reactor concept | MSR | ||||
| Fertile material | Thorium | ||||
| Status | Active | ||||
| Location | China | ||||
| |||||
| Coordinates | 38°57′37″N 102°36′44″E / 38.9602°N 102.6122°E / 38.9602; 102.6122 | ||||
| Main parameters of the reactor core | |||||
| Fuel (fissile material) | HALEU | ||||
| Fuel state | Liquid | ||||
| Neutron energy spectrum | Thermal | ||||
| Primary control method | Rods | ||||
| Primary moderator | Graphite | ||||
| Primary coolant | FLiBe | ||||
| Reactor usage | |||||
| Primary use | Prototyping | ||||
| Power (thermal) | 2 MW | ||||
| Criticality (date) | 11 Oct 2023 | ||||
| Operator/owner | SINAP | ||||
TMSR-LF1 (Chinese: 液态燃料钍基熔盐实验堆 lit.: "liquid fuel thorium-based molten salt experimental reactor") is a 2 MWt molten salt reactor (MSR) prototype operating in northwest China.[1][2][3][4][location note]
The project is a collaboration of "nearly 100 domestic research institutions, universities and industrial companies", "dedicated to molten salt reactors and thorium-uranium fuel cycle studies".[5]
History
The "LF" (liquid fuel) design is directly based on the 1960s Molten-Salt Reactor Experiment.[6] The site selected for the TMSR-LF1 is part of an industrial park[7] for the chemical and energy sectors, in a sparsely populated, arid region.[location note] Site construction began in 2018.[8] At the groundbreaking, a Taoist ceremony was held; after images of it went viral in China (an atheist state), CAS disciplined staff members, and issued a public apology.[9]
A reactor construction permit was issued by the Chinese National Nuclear Safety Administration in January 2020.[10] Unforeseen delays were caused by the COVID-19 pandemic in China.[11] Installation of equipment was finished in 2022.[5] Over 90 percent of the reactor's components are domestically produced, with 100 percent localization of key parts and a fully independent supply chain.[12]
Testing followed;[13][14] in August 2022, the Chinese Ministry of Ecology and Environment informed SINAP that its commissioning plan for the LF1 had been approved.[8] A ten-year operating license was issued in June 2023.[15][16] For the first 5–8 years, it is to be run in batch mode, before converting to continuous mode.[8]
Criticality was first achieved on 11 October 2023.[17][18][19] On 17 June 2024, full power (2MWt) operation was achieved.[19] In September, it received a license to load thorium into the molten salt, the initial loading of which happened the following month,[5] and on 8 October, it operated at full power for 10 days with thorium in the molten salt; Protactinium-233 was detected, indicating successful nuclear breeding.[19][20][21]
Specifications
The TMSR-LF1 is a Generation IV reactor constructed with the following specifications:[22][23][24]
- Thermal power: 2 MW
- Fuel salt: FLiBe (>99.95% Li-7) with fluorides of zirconium, uranium (HALEU: 19.75% U-235), and thorium
- inlet temperature: 630 °C
- outlet temperature: 650 °C
- volume: 1.68 m3
- flow rate: ~50 kg/s
- Coolant salt: FLiBe
- inlet temperature: 560 °C
- outlet temperature: 580 °C
- flow rate: ~42 kg/s
- Cover gas: Argon (0.05 MPa)
- volume: 1.6 m3
- Moderator: nuclear graphite
- Structural Material: UNS N10003 superalloy
- Lifetime: 10 years
- equivalent full power days: 300
- maximum full power days per year: 60
The reactor is located underground, seated at the bottom of a 14m (46 foot) deep dry well, which is capped at ground level, and above which rises a 20m (66 foot) tall roofed atrium.[25]
References
- http://finance.eastmoney.com/news/1350,20180329850624284.html Archived 8 July 2018 at the Wayback Machine 实验平台及配套项目拟选址于武威市民勤县红砂岗工业集聚区,南侧紧邻纬七路、东侧紧邻东环路。
- Tennenbaum, Jonathan (4 February 2020). "Molten salt and traveling wave nuclear reactors". Asia Times. Retrieved 30 September 2020.
- Liu, Yafen; Yan, Rui; Zou, Yang; Yu, Shihe; Zhou, Bo; Kang, Xuzhong; Hu, Jifeng; Cai, Xiangzhou (2020). "Sensitivity/Uncertainty comparison and similarity analysis between TMSR-LF1 and MSR models". Progress in Nuclear Energy. 122 103289. doi:10.1016/j.pnucene.2020.103289.
- "The off-line installation and start-up of the thorium-based molten salt experimental reactor body and the first cooling salt discharge". SINAP (in Chinese (China)). 23 December 2020. Retrieved 4 January 2021.
- Wu Wanzhen, and Li Menghan (1 November 2025). "China achieves 1st thorium-to-uranium fuel conversion in molten salt reactor". China Daily. Part 4. Retrieved 6 November 2025.
- Richard Martin (2 August 2016). "Fail-Safe Nuclear Power". MIT Technology Review. Retrieved 27 July 2021.
- "民勤红沙岗工业园区". Website of Wuwei, Gansu. 15 April 2021. Retrieved 23 August 2022.
民勤红沙岗工业园区位于民勤县红砂岗镇 ["Minqin Hongshagang Industrial Park is located in Hongshagang Town, Minqin County"...] 低碳新能源产业区:位于规划区东部,以第四代反应堆核能系统—钍基熔盐堆核能系统(TMSR)项目为基础,拓展高温制氢、布雷顿循环发电和二氧化碳资源利用,建成模块化钍基熔盐示范堆、大规模低碳新能源示范系统等,形成以模块化钍基熔盐堆为核心的低碳高效复合能源系统研发、示范与产业化基地。["Low-carbon new energy industrial zone: located in the east of the planning area, based on the fourth-generation reactor nuclear energy system-thorium-based molten salt reactor nuclear energy system (TMSR) project, to expand high-temperature hydrogen production, Brayton cycle power generation and carbon dioxide resource utilization, and build modules. A thorium-based molten salt demonstration reactor, a large-scale low-carbon new energy demonstration system, etc., have formed a low-carbon and high-efficiency composite energy system R&D, demonstration and industrialization base with a modular thorium-based molten salt reactor as the core."]
- "Chinese molten-salt reactor cleared for start up". World Nuclear News. World Nuclear Association. 9 August 2022. Retrieved 9 August 2022.
- "2 nuclear scientists suspended for failing to stop Taoist ritual". China Daily. 2 May 2018. Retrieved 16 June 2023.
- "2020 Annual Report" (PDF). National Nuclear Safety Administration (China). Retrieved 2 March 2025. The 2029 NNSA annual report states that "On January 13, 2020, the Construction Permit for the 2MWt TMSR-LF was issued."
- Ritsuo Yoshioka (2024). John Kutsch, and Thomas James Dolan (ed.). Global Progress on Molten Salt Reactors, Second Edition. Woodhead Publishing. p. 12. ISBN 9780323991292. Retrieved 7 November 2025.
- Wu Wanzhen, and Li Menghan (1 November 2025). "China achieves 1st thorium-to-uranium fuel conversion in molten salt reactor". China Daily. Part 5. Retrieved 6 November 2025.
- Stephen Chen (19 July 2021). "Could China's molten salt nuclear reactor be a clean, safe source of power?". South China Morning Post. Retrieved 31 July 2021.
- Mallapaty, Smriti (2021). "China prepares to test thorium-fuelled nuclear reactor". Nature. 597 (7876): 311–312. doi:10.1038/d41586-021-02459-w. PMID 34504330.
- "China's experimental molten salt reactor receives licence". Nuclear Engineering International. 20 June 2023. Retrieved 8 April 2024.
- "关于颁发2MWt液态燃料钍基熔盐实验堆运行许可证的通知". Ministry of Ecology and Environment (China). 7 June 2023. Retrieved 15 June 2023.
- Chen, Stephen (26 July 2024). "China sets launch date for world's first thorium molten salt nuclear power station". South China Morning Post. Retrieved 29 July 2024.
[TMSR-LF1] achieved criticality, or sustainable, chain nuclear reaction in October.
- "2023 Annual Report on Nuclear Safety" (PDF). National Nuclear Safety Administration (China). Retrieved 2 March 2025. The 2023 NNSA annual report states that TMSR-LF1 was "in operation", had "achieved its first criticality at 11:08 AM on October 11", and SINAP had reactor operator licenses for 15 people, of whom 8 were classified as "senior operators".
- Krepel, Jiri (22 January 2025). "Overview and Update of MSR Activities within GIF". Generation IV International Forum. pp. 71–72. Retrieved 27 February 2025.
At 11:08 on October 11, 2023, TMSR-LF1 achieved first criticality. At 12:10 on June 17, 2024, 2MWt full power operation was achieved. On October 8, 2024, TMSR-LF1 operated at full power for 10 days with thorium fuel, and Pa-233 was detected
- Wu Wanzhen, and Li Menghan (1 November 2025). "China achieves 1st thorium-to-uranium fuel conversion in molten salt reactor". China Daily. Part 1. Retrieved 6 November 2025.
- "Chinese molten salt reactor achieves conversion of thorium-uranium fuel". World Nuclear Association. 4 November 2025. Retrieved 4 November 2025.
- Hongjie Xu. Shanghai Institute of Applied Physics (SINAP), Chinese Academy of Sciences (CAS) (27 September 2018). "Progress of TMSR in China" (PDF). Retrieved 25 May 2021.
- Yang Zou. SINAP, CAS (4–5 July 2019). "Research Progress of TMSR design" (PDF). Retrieved 25 May 2021.
- Chen, Chang-Qi; Xia, Xiao-Bin; Zhang, Zhi-Hong; Cai, Jun; Li, Chang-Yuan (2019). "Radiological environmental impact analysis of a 2-MW thorium molten salt reactor during an accident". Nuclear Science and Techniques. 30 (5): 78. Bibcode:2019NuScT..30...78C. doi:10.1007/s41365-019-0605-3. ISSN 1001-8042. S2CID 145927937.
- Rencong Dai, Wei Gong, Xiao Wang, Xiaoyan Wang, Decheng Cui (31 January 2024). "Conservativeness Study on the Seismic Analysis Method for Research Reactor Plant Structure Based on TMSR-LF1". Advances in Civil Engineering. 2024 (1) 1672269. Hindawi. doi:10.1155/2024/1672269.
{{cite journal}}: CS1 maint: multiple names: authors list (link) (Licensed CC BY 4.0)
Location Notes
See also "Maps" section of the lede's infobox. The most recently published official site plan map is Figure 2.1-2 in
^LF1 Location: the LF1 reactor is sited within an industrial park located in Hongshagang (town), Minqin (county), Wuwei (prefecture), Gansu (province), China. The area is a semi-desert just south of the Badain Jaran section of the Gobi. As per official documentation, the TMSR-LF1 site is located at 38°57'31" N, 102°36'55" E. However, due to the China GPS shift problem, the reactor location using Western GPS coordinates is approximately 38°57′37″N 102°36′44″E / 38.9602°N 102.6122°E / 38.9602; 102.6122 (about a third of a kilometer offset).
External links
- Molten Salt Reactors ("China's dual programme" section) from the World Nuclear Association
- Status of Molten Salt Reactor Technology 2023 IAEA Technical Report; see Section 5.3 (R&D activities in China)
- 科技推动力·钍基熔盐堆建成 我国核能科技实现新突破 2025 CCTV-13 news broadcast (in Chinese; "Technological Driving Force: Thorium-based Molten Salt Reactor Completed, Marking a New Breakthrough in my country's Nuclear Energy Technology")